Community & Institutional Upgrading
Phased upgrading of a facility that has to stay open — barrier-free access, new halls, re-clad entrances.
- Category
- A&A Works
The usual constraint
A public programme calendar that cannot be suspended, so works must break into phases that each leave a usable set of rooms and a compliant escape route.
How we sequence it
- 1
Divide the building into work zones, each with its own hoarding line, escape route and fire-protection provision.
- 2
Schedule the noisiest demolition into holiday and low-usage periods agreed with the operator.
- 3
Review temporary fire-safety arrangements with the operator at every phase change.
Typical scope
- Barrier-free access ramps and lift installation
- New multi-purpose halls and acoustic treatment
- Entrance re-cladding and signage
- Toilet and wet-area reconstruction
- Electrical and mechanical ventilation upgrading
Other projects
Have a project in mind? Let's talk about what it really takes.
Send us the brief, the budget and the date that matters. You will get a straight read on feasibility within two working days — not a sales call.
Islandwide across Singapore · Enquiries acknowledged within 2 working days